Prosurv Consult provided Project Management, QS and CDMC for the demolition of the former Royal Doulton factory which comprised of 42 industrial buildings and offices adjacent to a number of listed buildings which remain. The works included the removal of slabs, foundations and the disconnection of existing services, to form a level site for future development.

Contract Value - £25,000 Credit(Off-set credit £600,000 for salvage material)

Programme – 20 weeks