Construction of new £25m rail manufacturing facility progressing on programme

18th January 2018

Works on the new £25 million Rail Manufacturing Facility at Celtic Business Park, Llanwern are progressing with the cladding and roofing due for completion by the end of February.

Blockwork on the 15,321 m2 factory building is due to commence later this month alongside the internal slabs. External works are also ongoing.

The works will include rail infrastructure to serve the rail testing and manufacturing facilities as well as a connection to existing rail infrastructure adjacent to the site and is due for completion in July 2018. 